Construction Update September 30th, 2015
 Lots of prep work happening for footers and ground work for the ride. Parts of the lakes are filled and getting ready for footings. Lots of new track out in the storage area with lift hill sections and the base of the lift has arrived. Overall the site is moving along and hope to see vertical construction end of October.
Mako Construction Updates for September to October 2015
Thumbnails
Construction Photos
Construction Update October 29th, 2015
Lots of footing work is still on going at the Mako site. Out in the lake there are lots of new holes for footings to be installed. The station and transfer area footings are ready to pour. Tons of other work going on around the site. Lots more track and supports have arrived as vertical construction nears.